KEY PROJECT PHASES
November 2016
CBC/Radio-Canada’s Board of Directors approves finalists for construction of new Maison de Radio-Canada (Broccolini) and revitalization of existing site (Groupe Mach).
April 2017
Government signs off on plan.
Summer 2017
Preliminary work completed and construction begins on new Maison de Radio-Canada.
Summer 2018
Central Equipment Room delivered.
Late 2019
Construction of new Maison de Radio-Canada completed.
2020
Radio-Canada moves into new facility and site revitalization work begins.